The week before Memorial Day, the company called 360construction had taken over the three phase project which included a 23' X 19' patio for phase 1, a set of 6 curved steps for the front porch for phase 2, and driveway, apron, gutter and curbs for phase 3 all in concrete when the first company was incapable of completing it. Two guys, Kenny and Jerred, had arrived to pick up where the first company stopped which was after excavation, framing, and gravel was placed. They did not check the first company's work as per original instruction of design nor did they determine if what was already done correct. Kenny and Jerred immediately began pouring concrete. With just one person moving the concrete with a single wheelbarrow from the street around the side of the house, up a small slope to the other side of the house while the other person worked the concrete, it became very apparent very fast that these two guys came ill-prepared both equipment wise and in man power especially in the heat of the day. The end result was the framing was up too high above the ground causing them to run out of concrete by a surface area of about 5' X 5' X 5". Hence, the entire pad had to be removed using a jackhammer the next day. On the succeeding day, the framing was lowered but I had noticed it seemed shorter. We had checked the measurements and found the patio area was short by 2'. We asked that it be redone and they said they would. We had seen them move the frames out further but did not see them remeasure but assumed they had even though we did not remeasure. They said it was only off about an inch or so. Round 2 on pouring the patio came a day later with a motorized wheelbarrow but still only Kenny and Jerred. It had gone a little better although the wheelbarrow did get stuck periodically. Kenny had spent his time on the motorized wheelbarrow and looked on while Jerred moved, leveled, and finished the concrete. As the patio was almost complete , they remarked how the step would be put in at the time the driveway was laid. The time period now is the beginning of June. As you may have already surmised, they were not there everyday nor did they always put in a full day's work when they were there. They also did not clean up their work area each day. The second phase of the the project was to create a set of 6 steps for the front porch. This is when they started not showing up for one reason or another for days at a time periodically. They began the step phase of the project by taking a couple of measurements one morning having arrived at 11:30 but then announced at 12 noon they had to leave in order to pay some bills but would be back in an hour. An hour had gone by, then two so we called them. They were having lunch but said it was a working lunch since they were designing my front steps and discussing how they would build the frame. Once they arrived, we asked to see the design they worked on over lunch. They said it wasn't finished but we asked to see what they had thus far. They could not produce anything and said they still needed to take a couple more measurements before they could finish. After the measurements were taken, they asked my husband to draw the plans up on his computer using the autocad program he has since they were having difficulty drawing it. So my husband drew up and labeled all measurements and parts of the steps after he directed them to take specific measurements other than those they had taken. My husband and I thought that they would build the frame for it that day but they said it was too late and they did not have the materials they needed to build it. Another day lost. The next day they brought some materials but it took them a while to figure out how to make a frame for it and position it to stay. Again we had noted that Jerred did most of the work while Kenny looked on. It took the entire day to do just that. The succeeding day was when the steps were poured but problems arose when the frame which was nailed not screwed was separating out to the side and to the front of the top step due to the mass of weight. They had not tied the steps together on the top and sides. They did recover. This was finished around June 11th. Again, they did not clean up the work area at the end of each day. It was not unusual to see bottles, food wrappers, and even tools laying in the last place they were used. The last phase of the project proved to be very difficult because it needed to be re-excavated, after gravel was laid because it did not provide the necessary gentle slope requested for the driveway. We had assumed the driveway, apron, gutter and curbs would be poured in one day but they said it would take at least 4 different pour days to do it since they were going to do it in sections. They had developed a habit of framing one day then a couple days later pour a section, then not show up again for a couple of days to fame another section then a few days later pour another section. We asked if the gravel was ever tamped down on the first section. They said it didn't need it. The second section had even more gravel and it was requested that they tamp it down. Again, as with the previous section and the other 2 phases of the project, Jerred did most of the work while Kenny sat and talked or he would just lean on a shovel or rake and smoke. After the second section was poured, we had noted what seemed to be a cavity on the one corner of the second section. The gutter and curbs were framed and poured along with the step on the patio. The step was done by Kenny who seemed put-out by us wanting the step to be completed at this time. He did not use a square and splattered concrete up onto the white enamel of the storm door which he never cleaned off. After it was poured and finished, the leftover concrete in the wheelbarrow along with the shovel laying in the concrete sat outside the backdoor next to the step for a couple of days. As for the gutter, we had insisted it not have a damming effect on the one end and there would be consistent flow from one side to the other. We also wanted the approach a little wider so this meant the curb would be shorter than previous. We ended up having a dam effect on the one end and 2 small birdbaths in the gutter near the middle and the curb cut off the approach making it more difficult to come onto the drive without swinging out first. The apron had not been poured yet. At this point, the date is now around June 21st. As with the first 2 parts of the project, we have taken pictures from beginning to end. This was also documented. They were fired and a third crew came in to pour and finish the apron and tear out and replace the gutter and curbs. This third crew had also cut all expansion joints in the patio and drive. It was at this point that they commented on how odd the dimensions were on the patio. The patio length running parallel next to the house was 22' 3'' and farthest from the house was 22' 9" while the width on one end was 20' and the width on the other end was 19' 5". They lied to us stating it was "only off an inch or so." To say the least, we were extremely patient and understanding about the weather but we were taken advantage of, lied to, our intellect, time, requests, expectations, and personal property were disrespected, and we did not get our money's worth. They lacked business sense, experience, skill, time management capabilities (wasted large amounts of time and could not plan ahead for what was to come--they stated it was "part of the process which you do not seem to understand"), and a high degree of respect for the customer along with a lack of communication since they would rarely return your calls or answer their phone. They were unable to keep their word, would not show up on time or at all, were often unprepared to do the task due to skill level, materials or lack of equipment. They are an insult to this field(s) of expertise.